Re: Change Cost Center in ME51n/ME52n whenever a line item is changed

$
0
0

Dear Raymond,

 

Thanks for your reply.

 

As i have posted my code in IF_EX_ME_PROCESS_PO_CUST~PROCESS_ACCOUNT only but its working fine whenever a new line item is created.

 

But whenever am trying to change the same line the method IF_EX_ME_PROCESS_PO_CUST~PROCESS_ACCOUNT is not getting triggered, where i can set the value of cost center.

 

But the method IF_EX_ME_PROCESS_PO_CUST~PROCESS_ITEM is triggering whenever am changing the line item.

 

Kindly suggest me how to change the cost center value whenever am changing the line item.

 

Thanks

Vijayan R.